Our 2025 report says 41,200 containers handled, 97% diverted, 3,380 metric tons of CO₂e avoided. Here is the same year described by the person who physically moved most of it.

Sheet
96
Revision
2026-10
Scale
1:1
Drawn at
Peoria IL
41,200Containers handled
165Per working day
4Times each is touched
11 miForklift travel per day
Lead the loopGot a container question of your own?A grader answers in writing, usually the same business day.
A mailbox you actually read — the quote comes by email.
US or Canada only, 10 digits — for example (309) 555-0137.
Two letters, US or Canada.
US ZIP (61615) or Canadian (M5V 2T6).

We only use this to quote your totes. No lists, no resale, no robo-calls. Fields marked * are required.

Forty-one thousand two hundred containers is a number from a report. One hundred and sixty-five containers a day, every working day, each one handled about four times, is the same fact described by somebody who had to do it.

StageTouchesWhyTime per container
Unload and stage at intake1Off the truck, into a grading row~45 sec
Grading line1Eighteen checks, photographs, sticker2–4 min
To wash, rebottle or fab1Sorted by path~40 sec
Rack or load out1Into inventory or onto a truck~50 sec
Containers that take the rebottling path are handled two to three additional times.

Where the day actually goes

About eleven miles of forklift travel across a four-acre yard, which sounds absurd until you count the trips. The single biggest operational improvement we have made in five years was not equipment — it was changing the yard layout so that containers move in one direction from the gate to the rack, with no backtracking. A container that has to be re-handled is a container losing money and emitting carbon for no reason.

  • Intake pad nearest the gate, because unloading a truck fast is how you keep a lane on schedule.
  • Grading line next, under fixed lighting, because grading in bad light is how you create a dispute.
  • Wash bays and rebottling bench in the middle, so sorted containers go left or right rather than back.
  • Fab bay and granulator at the far end, because those are terminal paths.
  • Racking and load-out on the outbound side, so a finished container never crosses the yard twice.

The 2025 year in physical terms

Report figureWhat it was physically
41,200 containers handled165 per working day, roughly 660 individual lifts
23,896 reused as-isWashed, inspected, racked — the busy half of the yard
8,652 rebottledAbout 35 a day on the bench, 40 minutes each of skilled work
2,472 repurposed10 a day through the fab bay, mostly harvesters and planters
4,944 recycled20 a day through the granulator, 504 tons of regrind out
1,142,000 gal water used4,600 gallons a day cycling through the sump
97% diversionFour residual streams, 12.8 tons, mostly consumables
3,380 t CO₂e avoidedNot visible from the seat at all — which is the point of publishing it

That last row is the honest tension in this business. Nothing about the environmental benefit is visible on the pad. What is visible is containers, straps, water, and a granulator we would rather not run. The arithmetic is real and it is also entirely abstract from where the work happens, which is why we publish the methodology rather than just the headline.

Three things that surprised us in the data

  1. Grading is the bottleneck, not washing. Two to four minutes per container on the grading line is more total time than the wash bay consumes, because washing runs in parallel and grading does not.
  2. The rebottling bench is our highest-value square footage. Thirty-five containers a day at roughly half the cost of replacement, each one saving 162 lb of CO₂e. If we expand anything, it is that bench.
  3. Repurposing is small and growing fastest. Six percent of throughput, up from nothing before the fab bay existed in 2018, and it absorbs exactly the containers that would otherwise be ground up.